Updated At: 2025-01-13 05:04:18
Running| Identification Phase Status | ||
| Date | Description | |
| No data found........... | ||
| Development Phase Status | ||
| Date | Description | |
| No data found........... | ||
| Procurement Phase Status | ||
| Date | Description | |
| 01-01-1970 | RFP document for selectin of private partner | |
| Award Phase Status | ||
| Date | Description | |
| No data found........... | ||
| Implementation Phase Status | ||
| Date | Description | |
| No data found........... | ||
|
|||||||||
| Information: | Details | ||||||||
| Project Summery | |||||||||
| Project Name: | Establishment of a 50-Seat Medical College and Nursing Institute and up-gradation and modernization of Existing Railway Hospital into 250 beds at Kamalapur in Dhaka | ||||||||
| Sector: | Health | ||||||||
| Location: | Dhaka | ||||||||
| Area: | Kamalapur in Dhaka (4.30 acres ) | ||||||||
| Background: | The Kamlapur railway hospital was established in 1986. It is situated between the Kamalapur station and Shahjahanpur junction. It is adjacent to the Motijheel Ideal School and College. The total area of the hospital covers 4.30 acres of land. There are also several trees in the hospital premises. Bangladesh Railway has decided to expand its social services in some other areas by utilizing its core asset including hues land base and other infrastructure. For the medical care of the BR’s employees, it has some hospitals at different places. Kamlapur Railway Hospital is one of them.
|
||||||||
| Project Scope: | Redevelopment of existing hospital facilities and development of a new medical college and nursing institute |
||||||||
| Objective: | • To provide medical services to common people as well as Bangladesh Railway’s employees. • To increase revenue earning potential of Bangladesh Railway. • To ensure more efficient utilization of Bangladesh Railway assets. |
||||||||
| Procurement Method: | |||||||||
| Key Features/Output: | |||||||||
| Economic Life: | |||||||||
| Contract Term: | 40 Years | ||||||||
| Construction Time: | 19 years phase wise construction Period | ||||||||
| Project Structure/Model | |||||||||
| PPP Structure: | Build, Operate and Transfer (BOT) | ||||||||
| PPP Reveneue Model: | Mixed Pay | ||||||||
| Project Estimated Cost per PFS/DFS | |||||||||
| Total Estimated Capital Cost: | |||||||||
| Total Project Cost: | BDT 800 crore | ||||||||
| Leverage (Debt to equity ratio): | |||||||||
| VGF amount %: | |||||||||
| Stakeholder Details | |||||||||
| Grantor: | Bangladesh Railway (BR) | ||||||||
| Division/Ministry: | Ministry of Railway | ||||||||
| Contracting Authority: | Bangladesh Railway (BR) | ||||||||
| Private Partner / Project Company: | Not Yet | ||||||||
| Shareholders (with Equity %): | |||||||||
| Lenders (with amount and %): | |||||||||
| EPC Contractor’s: | |||||||||
| O & M Contractor’s: | |||||||||
| Independent Engineer: | |||||||||
| Key dates | |||||||||
| Project Screening Date: | |||||||||
| In-Principle Approval Date: | 14-08-2013 | ||||||||
| Final Approval Date: | |||||||||
| Concession Signing Date: | |||||||||
| Concession Period: | |||||||||
| Financial Close: | |||||||||
| Construction Commencement Date: | |||||||||
| Construction Period: | |||||||||
| Construction Complete: | |||||||||
| Commercial Date of Operation(COD): | |||||||||
| Project Completion Date: | |||||||||
| Construction Contractor | |||||||||
| Not Yet | |||||||||
| TA Service Provider | |||||||||
| Feedback Infra Private Limited, India | |||||||||
| Present Phase | |||||||||
| Procurement Phase (LM Sends Contract To Legislative For Vetting) | |||||||||
| Note: | |||||||||
| ·
PPPTAF Application Form sent to PPP Office on 28.10.2013 for
appointment of Transaction Advisor. ·
Kamalapur Railway Hospital was converted into Railway General
Hospital on 30-04-2015. For this Transaction Advisor (TA) engagement was delayed. ·
Contract Agreement with Transaction Advisor [Powerwaterhouse
Coopers Ltd (PwC), India] signed on 28-05-2018. ·
Proposal has been sent to implement the project on Korean G to G
financing under PPP scheme. ·
Feasibility Study report has been approved on 31.08.2020. ·
PPP authority has given no objection to the bid document. Tenders
are scheduled to be called on 25.05.2021. ·
BR sent the bid document to MOR on 20-06-2021 for their review and
approval. ·
Approval of MOR on Bid Document sent by BR was received on
28.03.2022. ·
Tenders for the project were invited on 14.06.2022 and the last
date for submission of tenders is 25.10.2022. ·
The bid document was opened on 16.11.2022. One bidder submitted
the document for this project. ·
Evaluation of the submitted proposal is ongoing. TEC committee sent
a clarification letter to bidder on 30.05.3023. |
|||||||||